Skyrail (Ngong Ping 360) preliminary investigation report
*********************************************************

    In relation to the service interruption incident of the Skyrail system which occurred on June 17, the Skyrail Company submitted the Preliminary Investigation Report to the Electrical and Mechanical Services Department (EMSD) yesterday evening (June 22).  

     EMSD is now studying the Report in detail.  Follow up actions and on-site monitoring of tests conducted by the Skyrail Company will be undertaken by EMSD staff for confirming the cause of the incident and improvement measures required.

Ends/Friday, June 23, 2006
Issued at HKT 20:17