     The Drainage Services Department (DSD) is holding Relocation of Sha Tin Sewage Treatment Works to Caverns - Community Liaison Centre Open Day today and tomorrow (August 27 and 28). Aside from showcasing the latest developments of the Relocation of Sha Tin Sewage Treatment Works to Caverns project, the event is being held to celebrate the 25th anniversary of the establishment of the Hong Kong Special Administrative Region.
 
     The Secretary for Development, Ms Bernadette Linn, accompanied by the Director of Drainage Services, Ms Alice Pang, joined the public at the Open Day today and showed support for colleagues. Ms Linn then visited the works site in the cavern to learn about the progress and challenges of the works.
 
     The Relocation of Sha Tin Sewage Treatment Works to Caverns project is the largest cavern project in Hong Kong. Upon completion of the project, the environment of the existing Sha Tin Sewage Treatment Works and its surroundings will be enhanced, and about 28 hectares of land will be released. The DSD has applied innovative technologies and equipment in the project to enhance the efficiency and quality of the works, and to reduce the environmental impact and safety risks.
 
     The Open Day features exhibitions and game booths. DSD engineers are introducing cavern project highlights and the drill-and-blast construction method. Members of the public can also use the Immersive Cave Automatic Virtual Environmental System to view construction in the cavern, and learn about the cavern project and the work of the DSD in sewage treatment and flood prevention. In addition, members of the public can enjoy the sustainability design elements through touring the rain garden and the greening back garden of the Community Liaison Centre.
 
     For the details of the Open Day, please visit the website of the DSD (www.dsd.gov.hk/EN/What_s_New/What_s_New/news30811.html).
 
Ends/Saturday, August 27, 2022
Issued at HKT 15:18
NNNN
Today's Press Releases  

Photo

The Drainage Services Department (DSD) holds the Relocation of Sha Tin Sewage Treatment Works to Caverns - Community Liaison Centre Open Day today (August 27) and tomorrow (August 28), facilitating members of the public to learn about the cavern project and the work of the DSD in sewage treatment and flood prevention.
The Drainage Services Department (DSD) holds the Relocation of Sha Tin Sewage Treatment Works to Caverns - Community Liaison Centre Open Day today (August 27) and tomorrow (August 28), the members of the public can enjoy the sustainability design elements through touring around the outdoor gardens of the Community Liaison Centre.
The Drainage Services Department (DSD) holds the Relocation of Sha Tin Sewage Treatment Works to Caverns - Community Liaison Centre Open Day today (August 27) and tomorrow (August 28). Photo shows the Director of Drainage Services, Ms Alice Pang (first left) introducing cavern project highlights to members of the public.
The Drainage Services Department (DSD) holds the Relocation of Sha Tin Sewage Treatment Works to Caverns - Community Liaison Centre Open Day today (August 27) and tomorrow (August 28). Photo shows a visitor of using the Immersive Cave Automatic Virtual Environment System.
The Secretary for Development, Ms Bernadette Linn (third right), accompanied by the Director of Drainage Services, Ms Alice Pang (fourth right), attended the Relocation of Sha Tin Sewage Treatment Works to Caverns - Community Liaison Centre Open Day today (August 27).
The Secretary for Development, Ms Bernadette Linn (third right), accompanied by the Director of Drainage Services, Ms Alice Pang (first right), attended the Relocation of Sha Tin Sewage Treatment Works to Caverns - Community Liaison Centre Open Day today (August 27). Photo shows them visiting the works site in the cavern to learn about the progress and challenges of the works.